JHG – Melbourne Metro Early Works CBD North

image2The relocation of the following sewer, water and drainage services within Franklin St East, Franklin St West and A’Beckett St, Melbourne to facilitate the construction of the Melbourne Metro Tunnel main works:

  • 262m of DN150 and DN225 PVC Sewer Pipework using both open cut and trenchless methodologies
  • Construction of associated sewer manholes
  • 416m of 180PE and 280PE Water main pipework and associated valves and surface fittings
  • 300m of DN300, DN375 and DN525 Stormpro Drainage Pipework and associated pits and fittings
  • Testing, Tie-Ins and Commissioning.